NMSI Zambia are now active on 17 Mini Hospital (MH) sites with a further 1 Mini Hospital site resuming in the Luapula District during June, after being held by heavy rains earlier this year. The locations and construction sequencing of all 20 MH’s under the 15% programme remains provisionally agreed.

Other updates:

  • Nakachenje Mini Hospital ICM&T fit out and training is complete as well as site having permenant power
  • Mondengwa Mini Hospital is also approaching substantial completion followed by Kapanda and Kasongo MH’s in the Mansa District.
  • Following this, roll out of the remaining Mini Hospitals remains on target for completion every two weeks until completion of the 15% Phase of the Health Care Programme.