The NMSI team has had a year it can be proud of, matching and exceeding expectations. 50 sites have been handed over to the Ministry of Health in 2021; at the start of the year, the team aimed for 4 handovers per month and have managed to achieve an average of 4.2 per month.

Phase 1 and 2:
  Sites issued to contractor Sites complete Sites handed over ICMT equipped and trained Overall progress
Dec-21 99 76 49 67 75%
Awaiting certificates >>     3    
Jan-21 47 11 2 2 15%
2021 52 65 50 65  

 

Mini Hospitals:

  • Phase I: 20 Mini Hospitals is 100% complete.
  • 9 of the Phase I Mini Hospitals have completed their 12-month defects liability period.
  • Phase II: 49 have been handed over. A balance of 27 which are complete are pending electrification and water supply. 24 sites are currently at various stages of construction.
  • ICMT equipment and training has been carried out on a total of 67 sites.

 

District Hospitals:

  • Construction work on Mfuwe site is at 40%
  • Nchelenge: 15%
  • Kazembe: 5%
  • Kitwe: 2%
  • Ndola: To start in January 2022